proconsint.com

Gampaha, Attanagalla & Minuwangoda Integrated Water Supply Scheme

  • Type of Project

    Water Supply Project Planning and Management Consultancy Service

  • Description

    Government of Sri Lanka Funded Irrigation Project. Laying of DI/PVC Pipes, Fittings, Specials, DI Valves, Manhole Covers & Surface Boxes for Transmission & Distribution Mains in Attanagalla Area

  • Employee

    National Water Supply and Drainage Board (Project Employer)
    Sierra Construction Ltd - KDAW Construction JV (Contractors of the Project)
    Sierra Construction Ltd. (Project Contractor, Company's Client)

  • Location

    Attanagalla, Sri Lanka

  • Period

    February 2019 to May 2020

  • Value

    LKR 2.59 Billion

  • Contract No.

    P&D/C/GMAIWSS/ATTANAGALLA/2017/02

  • Scope of work

    Project Planning and Management Consultancy Service to main local Contractor M/S. Sierra Constructions Limited,
    Review and advise on baseline program,
    revised/recovery programs and segment-wise schedules, Identification and noticing time-related claim situations and Planning related letter writing and document controlling.
    Implementation of Framework for Project Risk Management. (Identification of Risk Sources, Identification of Risk Category, Identification of Risk Occurrence Probability, Risk Impact Identification, Risk Score Identification and Risk Occurrence Time Framing.)